Decision guide

Cross-Hole, PIT or mechanical admittance: which pile test should you choose?

Compare CSL, PIT and TRM by access, construction stage, objective and limitations when planning a pile investigation.

An unusual signal is not yet a diagnosis. The client needs to establish what information supports the decision and which test can obtain it under the actual pile conditions.

Start with the design decision

Establish whether the objective is concrete continuity, an expected length or a casting anomaly. These questions need different information, not a test selected solely because it is available.

Link each question to specific piles and records. Integrity and load-bearing capacity remain distinct; project decisions require more than one signal.

Access and construction stage

CSL requires accessible paths through installed tubes. PIT and TRM require pile-head working conditions suitable for the test, with existing connections and restraints considered.

Early planning avoids requesting an impractical configuration late in construction. Check access, tube or head conditions and geometric information before choosing.

Required information and coverage

CSL examines tube-to-tube paths; PIT interprets time-domain reflections; TRM considers force–velocity relationships in frequency. These are not equivalent representations of one volume.

The table compares opportunities and limitations, not automatic acceptance criteria. A second method is justified if it can clarify uncertainty and the site permits a meaningful measurement.

Campaign planning and deliverables

Agree identifiers, objectives, preparation and treatment of unreadable signals before testing. Do not set generic thresholds outside the project’s technical and contractual documentation.

Deliverables should explain coverage, conditions, assumptions and limitations. An uncertain finding may need further records or investigation, not a forced classification.

Comparison by survey objective

MethodPrincipleAccessExecution stageInformation obtainableMain limitationsTypical applications
Cross-Hole / CSLUltrasonic transmission between probesInstalled, traversable tubesPlanned before casting; measurement with accessible tubesSignal variations by path and depthTube-to-tube coverage; coupling or tube problemsInvestigation of concrete along installed paths
PIT / PEMLow-strain impulse reflectionsAccessible, suitable headWhen the head is available and concrete suitableReflections, estimated length and impedance changesAssumed velocity, attenuation, geometry and restraintsDimensional assessment and head-based anomaly investigation
Mechanical admittance / TRMVelocity/force relationship in frequencySuitable head; force and response acquisitionWhen consistent impact and measurement are possibleResonances, dimensional indications and inferred profileInterpretive model, ground and boundary conditionsFrequency-domain vibrational investigation

Related guides

Back to the main guide

Frequently asked questions

Do integrity tests measure load-bearing capacity?
No. They assess aspects of integrity or pile response within method limitations; they do not replace a load-capacity assessment.
Which method is always best?
None: the objective, access and pile conditions determine what information can be obtained.
Is estimated length certain?
No: it depends on velocity assumptions, identifying the response and boundary conditions.

References and documentary scope

What information does your project need?

Share the objective, site constraints and required deliverables so we can assess an appropriate survey strategy.